UTAS Stadium - 252008
Senaste bulletiner
  • 15th december 2025, Today's Activities & Hazards

    TOOLBOX TALK TODAY IN SITE COMPOUND AT 9:45AM. ALL ONSITE WORKERS TO ATTEND.

    Centre West:
    • BridgePro cutting & installing piles – EXCESSIVE NOISE – All workers in vicinity of pile hammering must wear ear protection. Stay out of exclusion zones.

    Western Infill:
    • Cooke & Dowsett continuing stormwater works – DEEP EXCAVATION – Keep out of their working area.
    • Platinum excavating for ground beams.
    • FB preparing Southern end raker walls & ground beams.

    Eastern Stand:
    • BridgePro cutting & installing piles – EXCESSIVE NOISE – All workers in vicinity of pile hammering must wear ear protection. Stay out of exclusion zones.

    Site Compound:
    • Degree C continuing site compound works.
    • Loading and unloading of deliveries.

    Site Hazards:
    • Storm Water Works – DEEP EXCAVATION – Stay out of fenced off working area
    • Pile Installation across all of site – Excessive noise & mobile plant movement. Stay out of exclusion zones and wear hearing protection where required.
    • Mobile plant movements – Be aware of all mobile plant movements. Keep out of exclusion zones.
    • Excavation – Make yourself known to excavators when moving around them.
    • Demolition – Noise & debris

  • 12th december 2025, Today's Activities & Hazards

    Centre West:
    • BridgePro cutting & installing piles – EXCESSIVE NOISE – All workers in vicinity of pile hammering must wear ear protection. Stay out of exclusion zones.

    Western Infill:
    • Cooke & Dowsett continuing stormwater works – DEEP EXCAVATION – Keep out of their working area.
    • BridgePro grouting tops of driven piles.
    • FB preparing Southern end raker walls.

    Eastern Stand:
    • BridgePro cutting & installing piles – EXCESSIVE NOISE – All workers in vicinity of pile hammering must wear ear protection. Stay out of exclusion zones.

    Site Compound:
    • Degree C continuing site compound works.
    • Loading and unloading of deliveries.

    Site Hazards:
    • Storm Water Works – DEEP EXCAVATION – Stay out of fenced off working area
    • Pile Installation across all of site – Excessive noise & mobile plant movement. Stay out of exclusion zones and wear hearing protection where required.
    • Mobile plant movements – Be aware of all mobile plant movements. Keep out of exclusion zones.
    • Excavation – Make yourself known to excavators when moving around them.
    • Demolition – Noise & debris

Väderprognos för byggarbetsplatsen
Nuvarande väder på platsen

Senast uppdaterad den: 14:21
Temperatur: 20°C (App 15°C)
Vindhastighet: 24KMH
Max. vind: 26KMH @13:21
Regn sedan klockan 9 på morgonen: 0,0mm
Min temp: 2°C @06:25
Max temp: 22°C @14:43 2026-04-13
Vindstöt: 26KMH
Max Gust: 32KMH @13:21


Observation hämtad från - Bureau of Meteorology
Observationsplats - Launceston, TASMANIA
Tidszon - östaustralisk normaltid
Prognos - tisdag, 14 april

Cloudy.
Min: 5°C Max: 18°C
Risk för regn: 10%


Prognos hämtad från - Bureau of Meteorology
Prognosplats - Launceston, TASMANIA
Tidszon - östaustralisk normaltid
Imorgon - onsdag, 15 april

Showers. Windy.
Min: 8°C Max: 19°C
Risk för regn: 90%
Förväntad nederbörd: 1 till 7mm


Viktiga platsdokument
Ny på platsen?

Känner du till kraven på personlig skyddsutrustning (PPE) för denna plats?

Se till att du har rätt skyddsutrustning för din första dag på byggarbetsplatsen.

Visa platsens krav på personlig skyddsutrustning

Kom igång med arbetet snabbare när du anländer till arbetsplatsen.

Slutför din platsregistrering online när det passar dig och spara tid.

Börja registreringen

Ny på platsen?

Känner du till kraven på personlig skyddsutrustning (PPE) för denna plats?

Se till att du har rätt skyddsutrustning för din första dag på byggarbetsplatsen.

Visa platsens krav på personlig skyddsutrustning

Ny på platsen?

Kom igång med arbetet snabbare när du anländer till arbetsplatsen.

Slutför din platsregistrering online när det passar dig och spara tid.

Börja registreringen