UTAS Stadium - 252008 - Offentlig byggarbetsplats
-
15th december 2025, Today's Activities & Hazards
TOOLBOX TALK TODAY IN SITE COMPOUND AT 9:45AM. ALL ONSITE WORKERS TO ATTEND.
Centre West:
• BridgePro cutting & installing piles – EXCESSIVE NOISE – All workers in vicinity of pile hammering must wear ear protection. Stay out of exclusion zones.
Western Infill:
• Cooke & Dowsett continuing stormwater works – DEEP EXCAVATION – Keep out of their working area.
• Platinum excavating for ground beams.
• FB preparing Southern end raker walls & ground beams.
Eastern Stand:
• BridgePro cutting & installing piles – EXCESSIVE NOISE – All workers in vicinity of pile hammering must wear ear protection. Stay out of exclusion zones.
Site Compound:
• Degree C continuing site compound works.
• Loading and unloading of deliveries.
Site Hazards:
• Storm Water Works – DEEP EXCAVATION – Stay out of fenced off working area
• Pile Installation across all of site – Excessive noise & mobile plant movement. Stay out of exclusion zones and wear hearing protection where required.
• Mobile plant movements – Be aware of all mobile plant movements. Keep out of exclusion zones.
• Excavation – Make yourself known to excavators when moving around them.
• Demolition – Noise & debris -
12th december 2025, Today's Activities & Hazards
Centre West:
• BridgePro cutting & installing piles – EXCESSIVE NOISE – All workers in vicinity of pile hammering must wear ear protection. Stay out of exclusion zones.
Western Infill:
• Cooke & Dowsett continuing stormwater works – DEEP EXCAVATION – Keep out of their working area.
• BridgePro grouting tops of driven piles.
• FB preparing Southern end raker walls.
Eastern Stand:
• BridgePro cutting & installing piles – EXCESSIVE NOISE – All workers in vicinity of pile hammering must wear ear protection. Stay out of exclusion zones.
Site Compound:
• Degree C continuing site compound works.
• Loading and unloading of deliveries.
Site Hazards:
• Storm Water Works – DEEP EXCAVATION – Stay out of fenced off working area
• Pile Installation across all of site – Excessive noise & mobile plant movement. Stay out of exclusion zones and wear hearing protection where required.
• Mobile plant movements – Be aware of all mobile plant movements. Keep out of exclusion zones.
• Excavation – Make yourself known to excavators when moving around them.
• Demolition – Noise & debris
Nuvarande väder på platsen
Senast uppdaterad den: 14:21
Temperatur: 20°C (App 15°C)
Vindhastighet: 24KMH
Max. vind: 26KMH @13:21
Regn sedan klockan 9 på morgonen: 0,0mm
Min temp: 2°C @06:25
Max temp: 22°C @14:43 2026-04-13
Vindstöt: 26KMH
Max Gust: 32KMH @13:21
Observationsplats - Launceston, TASMANIA
Tidszon - östaustralisk normaltid
Prognos - tisdag, 14 april
Cloudy.
Min: 5°C Max: 18°C
Risk för regn: 10%
Prognosplats - Launceston, TASMANIA
Tidszon - östaustralisk normaltid
Imorgon - onsdag, 15 april
Showers. Windy.
Min: 8°C Max: 19°C
Risk för regn: 90%
Förväntad nederbörd: 1 till 7mm
Känner du till kraven på personlig skyddsutrustning (PPE) för denna plats?
Se till att du har rätt skyddsutrustning för din första dag på byggarbetsplatsen.
Kom igång med arbetet snabbare när du anländer till arbetsplatsen.
Slutför din platsregistrering online när det passar dig och spara tid.
Känner du till kraven på personlig skyddsutrustning (PPE) för denna plats?
Se till att du har rätt skyddsutrustning för din första dag på byggarbetsplatsen.
Kom igång med arbetet snabbare när du anländer till arbetsplatsen.
Slutför din platsregistrering online när det passar dig och spara tid.