UTAS Stadium - 252008 - Site du projet public
-
15th décembre 2025, Today's Activities & Hazards
TOOLBOX TALK TODAY IN SITE COMPOUND AT 9:45AM. ALL ONSITE WORKERS TO ATTEND.
Centre West:
• BridgePro cutting & installing piles – EXCESSIVE NOISE – All workers in vicinity of pile hammering must wear ear protection. Stay out of exclusion zones.
Western Infill:
• Cooke & Dowsett continuing stormwater works – DEEP EXCAVATION – Keep out of their working area.
• Platinum excavating for ground beams.
• FB preparing Southern end raker walls & ground beams.
Eastern Stand:
• BridgePro cutting & installing piles – EXCESSIVE NOISE – All workers in vicinity of pile hammering must wear ear protection. Stay out of exclusion zones.
Site Compound:
• Degree C continuing site compound works.
• Loading and unloading of deliveries.
Site Hazards:
• Storm Water Works – DEEP EXCAVATION – Stay out of fenced off working area
• Pile Installation across all of site – Excessive noise & mobile plant movement. Stay out of exclusion zones and wear hearing protection where required.
• Mobile plant movements – Be aware of all mobile plant movements. Keep out of exclusion zones.
• Excavation – Make yourself known to excavators when moving around them.
• Demolition – Noise & debris -
12th décembre 2025, Today's Activities & Hazards
Centre West:
• BridgePro cutting & installing piles – EXCESSIVE NOISE – All workers in vicinity of pile hammering must wear ear protection. Stay out of exclusion zones.
Western Infill:
• Cooke & Dowsett continuing stormwater works – DEEP EXCAVATION – Keep out of their working area.
• BridgePro grouting tops of driven piles.
• FB preparing Southern end raker walls.
Eastern Stand:
• BridgePro cutting & installing piles – EXCESSIVE NOISE – All workers in vicinity of pile hammering must wear ear protection. Stay out of exclusion zones.
Site Compound:
• Degree C continuing site compound works.
• Loading and unloading of deliveries.
Site Hazards:
• Storm Water Works – DEEP EXCAVATION – Stay out of fenced off working area
• Pile Installation across all of site – Excessive noise & mobile plant movement. Stay out of exclusion zones and wear hearing protection where required.
• Mobile plant movements – Be aware of all mobile plant movements. Keep out of exclusion zones.
• Excavation – Make yourself known to excavators when moving around them.
• Demolition – Noise & debris
Météo sur le site actuel
Dernière mise à jour: 00:21
Température: 16C (App 16C)
Vitesse du vent: 4KMH
Max. Vent: 4KMH @00:21
Précipitations depuis 9 h: 4,8mm
Temp min.: 15C @00:02
Temp. max: 28C @15:42 14/01/2026
Rafale de vent: 6KMH
Rafales max: 6KMH @00:21
Lieu d'observation - Launceston, TASMANIA
Fuseau horaire - heure normale de l’Est de l’Australie
Prévision - jeudi, 15 janvier
Partly cloudy.
Min: 11C Max: 24C
Risque de pluie: 5%
Lieu en prévision - Launceston, TASMANIA
Fuseau horaire - heure normale de l’Est de l’Australie
Demain - vendredi, 16 janvier
Partly cloudy.
Min: 11C Max: 24C
Risque de pluie: 5%
Connaissez-vous les exigences en matière de PPE pour ce site ?
Assurez-vous que vous avez l'équipement de sécurité approprié lors de votre premier jour sur le site.
Commencez à travailler plus tôt dès votre arrivée sur le site.
Complétez votre inscription du site en ligne à votre convenance et gagnez du temps par la même occasion.
Connaissez-vous les exigences en matière de PPE pour ce site ?
Assurez-vous que vous avez l'équipement de sécurité approprié lors de votre premier jour sur le site.
Commencez à travailler plus tôt dès votre arrivée sur le site.
Complétez votre inscription du site en ligne à votre convenance et gagnez du temps par la même occasion.