UTAS Stadium - 252008 - Openbare Project Locatie
-
15th december 2025, Today's Activities & Hazards
TOOLBOX TALK TODAY IN SITE COMPOUND AT 9:45AM. ALL ONSITE WORKERS TO ATTEND.
Centre West:
• BridgePro cutting & installing piles – EXCESSIVE NOISE – All workers in vicinity of pile hammering must wear ear protection. Stay out of exclusion zones.
Western Infill:
• Cooke & Dowsett continuing stormwater works – DEEP EXCAVATION – Keep out of their working area.
• Platinum excavating for ground beams.
• FB preparing Southern end raker walls & ground beams.
Eastern Stand:
• BridgePro cutting & installing piles – EXCESSIVE NOISE – All workers in vicinity of pile hammering must wear ear protection. Stay out of exclusion zones.
Site Compound:
• Degree C continuing site compound works.
• Loading and unloading of deliveries.
Site Hazards:
• Storm Water Works – DEEP EXCAVATION – Stay out of fenced off working area
• Pile Installation across all of site – Excessive noise & mobile plant movement. Stay out of exclusion zones and wear hearing protection where required.
• Mobile plant movements – Be aware of all mobile plant movements. Keep out of exclusion zones.
• Excavation – Make yourself known to excavators when moving around them.
• Demolition – Noise & debris -
12th december 2025, Today's Activities & Hazards
Centre West:
• BridgePro cutting & installing piles – EXCESSIVE NOISE – All workers in vicinity of pile hammering must wear ear protection. Stay out of exclusion zones.
Western Infill:
• Cooke & Dowsett continuing stormwater works – DEEP EXCAVATION – Keep out of their working area.
• BridgePro grouting tops of driven piles.
• FB preparing Southern end raker walls.
Eastern Stand:
• BridgePro cutting & installing piles – EXCESSIVE NOISE – All workers in vicinity of pile hammering must wear ear protection. Stay out of exclusion zones.
Site Compound:
• Degree C continuing site compound works.
• Loading and unloading of deliveries.
Site Hazards:
• Storm Water Works – DEEP EXCAVATION – Stay out of fenced off working area
• Pile Installation across all of site – Excessive noise & mobile plant movement. Stay out of exclusion zones and wear hearing protection where required.
• Mobile plant movements – Be aware of all mobile plant movements. Keep out of exclusion zones.
• Excavation – Make yourself known to excavators when moving around them.
• Demolition – Noise & debris
Huidige weersomstandigheden op locatie
Laatst bijgewerkt om: 16:21
Temperatuur: 18C (App 15C)
Windsnelheid: 17KM/U
Max. Wind: 26KM/U @15:21
Regen sinds 9:00 uur: 0,0mm
Min.temp: 2C @06:25
Max.temp: 22C @14:43 13-4-2026
Windvlaag: 20KM/U
Max. windvlaag: 32KM/U @15:21
Waarneming Locatie - Launceston, TASMANIA
Tijdzone - Oost-Australische standaardtijd
Weerbericht - dinsdag, 14 april
Cloudy.
Min.: 5C Max.: 18C
Kans op neerslag: 10%
Weerbericht locatie - Launceston, TASMANIA
Tijdzone - Oost-Australische standaardtijd
Morgen - woensdag, 15 april
Showers. Windy.
Min.: 8C Max.: 19C
Kans op neerslag: 90%
Verwachte regen: 1 tot 7mm
Weet u wat de PBM-vereisten voor deze locatie zijn?
Zorg dat u voor uw eerste dag op de locatie de juiste veiligheidsapparatuur hebt.
Begin sneller te werken zodra u op de locatie aankomt.
Voltooi uw locatieregistratie eenvoudig online en bespaar zo kostbare tijd.
Weet u wat de PBM-vereisten voor deze locatie zijn?
Zorg dat u voor uw eerste dag op de locatie de juiste veiligheidsapparatuur hebt.
Begin sneller te werken zodra u op de locatie aankomt.
Voltooi uw locatieregistratie eenvoudig online en bespaar zo kostbare tijd.