UTAS Stadium - 252008 - Sitio del proyecto público
-
15th diciembre 2025, Today's Activities & Hazards
TOOLBOX TALK TODAY IN SITE COMPOUND AT 9:45AM. ALL ONSITE WORKERS TO ATTEND.
Centre West:
• BridgePro cutting & installing piles – EXCESSIVE NOISE – All workers in vicinity of pile hammering must wear ear protection. Stay out of exclusion zones.
Western Infill:
• Cooke & Dowsett continuing stormwater works – DEEP EXCAVATION – Keep out of their working area.
• Platinum excavating for ground beams.
• FB preparing Southern end raker walls & ground beams.
Eastern Stand:
• BridgePro cutting & installing piles – EXCESSIVE NOISE – All workers in vicinity of pile hammering must wear ear protection. Stay out of exclusion zones.
Site Compound:
• Degree C continuing site compound works.
• Loading and unloading of deliveries.
Site Hazards:
• Storm Water Works – DEEP EXCAVATION – Stay out of fenced off working area
• Pile Installation across all of site – Excessive noise & mobile plant movement. Stay out of exclusion zones and wear hearing protection where required.
• Mobile plant movements – Be aware of all mobile plant movements. Keep out of exclusion zones.
• Excavation – Make yourself known to excavators when moving around them.
• Demolition – Noise & debris -
12th diciembre 2025, Today's Activities & Hazards
Centre West:
• BridgePro cutting & installing piles – EXCESSIVE NOISE – All workers in vicinity of pile hammering must wear ear protection. Stay out of exclusion zones.
Western Infill:
• Cooke & Dowsett continuing stormwater works – DEEP EXCAVATION – Keep out of their working area.
• BridgePro grouting tops of driven piles.
• FB preparing Southern end raker walls.
Eastern Stand:
• BridgePro cutting & installing piles – EXCESSIVE NOISE – All workers in vicinity of pile hammering must wear ear protection. Stay out of exclusion zones.
Site Compound:
• Degree C continuing site compound works.
• Loading and unloading of deliveries.
Site Hazards:
• Storm Water Works – DEEP EXCAVATION – Stay out of fenced off working area
• Pile Installation across all of site – Excessive noise & mobile plant movement. Stay out of exclusion zones and wear hearing protection where required.
• Mobile plant movements – Be aware of all mobile plant movements. Keep out of exclusion zones.
• Excavation – Make yourself known to excavators when moving around them.
• Demolition – Noise & debris
Tiempo actual del emplazamiento
Última actualización en: 0:21
Temperatura: 16C (Aplicación 16C)
Velocidad del viento: 4Km / h
Max. Viento: 4Km / h @0:21
Lluvia desde las 9 a. m.: 4,8mm
Temperatura mínima: 15C @0:02
Temperaturas máximas: 28C @15:42 14/01/2026
Ráfaga: 6Km / h
Ráfagas máximas: 6Km / h @0:21
Ubicación de la observación - Launceston, TASMANIA
Huso horario - hora estándar de Australia oriental
Pronóstico - jueves, 15 enero
Partly cloudy.
Min: 11C Max: 24C
Probabilidad de lluvia: 5%
Pronóstico Ubicación - Launceston, TASMANIA
Huso horario - hora estándar de Australia oriental
Mañana - viernes, 16 enero
Partly cloudy.
Min: 11C Max: 24C
Probabilidad de lluvia: 5%
¿Conoce los requisitos de EPI para este emplazamiento?
Asegúrese de que cuenta con el equipo de seguridad correcto para su primer día en el emplazamiento.
Empiece a trabajar antes al llegar "in situ".
Complete su registro en el sitio web en línea a su conveniencia y ahorre tiempo.
¿Conoce los requisitos de EPI para este emplazamiento?
Asegúrese de que cuenta con el equipo de seguridad correcto para su primer día en el emplazamiento.
Empiece a trabajar antes al llegar "in situ".
Complete su registro en el sitio web en línea a su conveniencia y ahorre tiempo.