  • 15th prosince 2025, Today's Activities & Hazards

    TOOLBOX TALK TODAY IN SITE COMPOUND AT 9:45AM. ALL ONSITE WORKERS TO ATTEND.

    Centre West:
    • BridgePro cutting & installing piles – EXCESSIVE NOISE – All workers in vicinity of pile hammering must wear ear protection. Stay out of exclusion zones.

    Western Infill:
    • Cooke & Dowsett continuing stormwater works – DEEP EXCAVATION – Keep out of their working area.
    • Platinum excavating for ground beams.
    • FB preparing Southern end raker walls & ground beams.

    Eastern Stand:
    • BridgePro cutting & installing piles – EXCESSIVE NOISE – All workers in vicinity of pile hammering must wear ear protection. Stay out of exclusion zones.

    Site Compound:
    • Degree C continuing site compound works.
    • Loading and unloading of deliveries.

    Site Hazards:
    • Storm Water Works – DEEP EXCAVATION – Stay out of fenced off working area
    • Pile Installation across all of site – Excessive noise & mobile plant movement. Stay out of exclusion zones and wear hearing protection where required.
    • Mobile plant movements – Be aware of all mobile plant movements. Keep out of exclusion zones.
    • Excavation – Make yourself known to excavators when moving around them.
    • Demolition – Noise & debris

  • 12th prosince 2025, Today's Activities & Hazards

    Centre West:
    • BridgePro cutting & installing piles – EXCESSIVE NOISE – All workers in vicinity of pile hammering must wear ear protection. Stay out of exclusion zones.

    Western Infill:
    • Cooke & Dowsett continuing stormwater works – DEEP EXCAVATION – Keep out of their working area.
    • BridgePro grouting tops of driven piles.
    • FB preparing Southern end raker walls.

    Eastern Stand:
    • BridgePro cutting & installing piles – EXCESSIVE NOISE – All workers in vicinity of pile hammering must wear ear protection. Stay out of exclusion zones.

    Site Compound:
    • Degree C continuing site compound works.
    • Loading and unloading of deliveries.

    Site Hazards:
    • Storm Water Works – DEEP EXCAVATION – Stay out of fenced off working area
    • Pile Installation across all of site – Excessive noise & mobile plant movement. Stay out of exclusion zones and wear hearing protection where required.
    • Mobile plant movements – Be aware of all mobile plant movements. Keep out of exclusion zones.
    • Excavation – Make yourself known to excavators when moving around them.
    • Demolition – Noise & debris

Předpověď počasí pro stavbu
Aktuální počasí na pracovišti

Naposledy aktualizováno v: 14:21
Teplota: 20C (Aplikace 15C)
Rychlost větru: 24KMH
Max. vítr: 26KMH @13:21
Déšť od 9 ráno: 0,0mm
Min. teplota: 2C @6:25
Max. teplota: 22C @14:43 13.04.2026
Náraz větru: 26KMH
Max náraz větru: 32KMH @13:21


Pozorování vycházející z - Bureau of Meteorology
Místo pozorování - Launceston, TASMANIA
Časové pásmo - východoaustralský standardní čas
Předpověď – úterý, 14 dubna

Cloudy.
Min: 5C Max: 18C
Možnost deště: 10%


Předpověď pochází z – Bureau of Meteorology
Místo předpovědi – Launceston, TASMANIA
Časové pásmo - východoaustralský standardní čas
Zítra - středa, 15 dubna

Showers. Windy.
Min: 8C Max: 19C
Možnost deště: 90%
Očekávaný déšť: 1 k 7mm


Důležité dokumenty pracoviště
Novinka na pracovišti?

Znáte požadavky na OOPP pro toto pracoviště?

Ujistěte se, zda máte pro první den na pracovišti správné bezpečnostní vybavení.

Zobrazit požadavky na OOPP ke stavbě

Po příjezdu na místo můžete začít pracovat dříve.

Jakmile budete moci, dokončete registraci do pracoviště online, a ušetřete si tak čas.

Začít registraci

Novinka na pracovišti?

Znáte požadavky na OOPP pro toto pracoviště?

Ujistěte se, zda máte pro první den na pracovišti správné bezpečnostní vybavení.

Zobrazit požadavky na OOPP ke stavbě

Novinka na pracovišti?

Po příjezdu na místo můžete začít pracovat dříve.

Jakmile budete moci, dokončete registraci do pracoviště online, a ušetřete si tak čas.

Začít registraci