UTAS Stadium - 252008 - 공공 프로젝트 현장
-
15th 12월 2025, Today's Activities & Hazards
TOOLBOX TALK TODAY IN SITE COMPOUND AT 9:45AM. ALL ONSITE WORKERS TO ATTEND.
Centre West:
• BridgePro cutting & installing piles – EXCESSIVE NOISE – All workers in vicinity of pile hammering must wear ear protection. Stay out of exclusion zones.
Western Infill:
• Cooke & Dowsett continuing stormwater works – DEEP EXCAVATION – Keep out of their working area.
• Platinum excavating for ground beams.
• FB preparing Southern end raker walls & ground beams.
Eastern Stand:
• BridgePro cutting & installing piles – EXCESSIVE NOISE – All workers in vicinity of pile hammering must wear ear protection. Stay out of exclusion zones.
Site Compound:
• Degree C continuing site compound works.
• Loading and unloading of deliveries.
Site Hazards:
• Storm Water Works – DEEP EXCAVATION – Stay out of fenced off working area
• Pile Installation across all of site – Excessive noise & mobile plant movement. Stay out of exclusion zones and wear hearing protection where required.
• Mobile plant movements – Be aware of all mobile plant movements. Keep out of exclusion zones.
• Excavation – Make yourself known to excavators when moving around them.
• Demolition – Noise & debris -
12th 12월 2025, Today's Activities & Hazards
Centre West:
• BridgePro cutting & installing piles – EXCESSIVE NOISE – All workers in vicinity of pile hammering must wear ear protection. Stay out of exclusion zones.
Western Infill:
• Cooke & Dowsett continuing stormwater works – DEEP EXCAVATION – Keep out of their working area.
• BridgePro grouting tops of driven piles.
• FB preparing Southern end raker walls.
Eastern Stand:
• BridgePro cutting & installing piles – EXCESSIVE NOISE – All workers in vicinity of pile hammering must wear ear protection. Stay out of exclusion zones.
Site Compound:
• Degree C continuing site compound works.
• Loading and unloading of deliveries.
Site Hazards:
• Storm Water Works – DEEP EXCAVATION – Stay out of fenced off working area
• Pile Installation across all of site – Excessive noise & mobile plant movement. Stay out of exclusion zones and wear hearing protection where required.
• Mobile plant movements – Be aware of all mobile plant movements. Keep out of exclusion zones.
• Excavation – Make yourself known to excavators when moving around them.
• Demolition – Noise & debris
현재 현장 날씨
마지막 업데이트 날짜: 오전 12:21
온도: 16씨 (앱 16씨)
풍속: 4KMH
최대 풍속: 4KMH @오전 12:21
오전 9시부터 비가 내림: 4.8음음
최저 기온: 15씨 @오전 12:02
최고 온도: 28씨 @오후 3:42 2026-01-14
돌풍: 6KMH
최대 돌풍: 6KMH @오전 12:21
관찰 위치 - Launceston, TASMANIA
시간대 - 오스트레일리아 동부 표준시
예측 - 목요일, 15 1월
Partly cloudy.
분: 11씨 맥스: 24씨
비 올 확률: 5%
예측 위치 - Launceston, TASMANIA
시간대 - 오스트레일리아 동부 표준시
내일 - 금요일, 16 1월
Partly cloudy.
분: 11씨 맥스: 24씨
비 올 확률: 5%