  • 15th 12월 2025, Today's Activities & Hazards

    TOOLBOX TALK TODAY IN SITE COMPOUND AT 9:45AM. ALL ONSITE WORKERS TO ATTEND.

    Centre West:
    • BridgePro cutting & installing piles – EXCESSIVE NOISE – All workers in vicinity of pile hammering must wear ear protection. Stay out of exclusion zones.

    Western Infill:
    • Cooke & Dowsett continuing stormwater works – DEEP EXCAVATION – Keep out of their working area.
    • Platinum excavating for ground beams.
    • FB preparing Southern end raker walls & ground beams.

    Eastern Stand:
    • BridgePro cutting & installing piles – EXCESSIVE NOISE – All workers in vicinity of pile hammering must wear ear protection. Stay out of exclusion zones.

    Site Compound:
    • Degree C continuing site compound works.
    • Loading and unloading of deliveries.

    Site Hazards:
    • Storm Water Works – DEEP EXCAVATION – Stay out of fenced off working area
    • Pile Installation across all of site – Excessive noise & mobile plant movement. Stay out of exclusion zones and wear hearing protection where required.
    • Mobile plant movements – Be aware of all mobile plant movements. Keep out of exclusion zones.
    • Excavation – Make yourself known to excavators when moving around them.
    • Demolition – Noise & debris

  • 12th 12월 2025, Today's Activities & Hazards

    Centre West:
    • BridgePro cutting & installing piles – EXCESSIVE NOISE – All workers in vicinity of pile hammering must wear ear protection. Stay out of exclusion zones.

    Western Infill:
    • Cooke & Dowsett continuing stormwater works – DEEP EXCAVATION – Keep out of their working area.
    • BridgePro grouting tops of driven piles.
    • FB preparing Southern end raker walls.

    Eastern Stand:
    • BridgePro cutting & installing piles – EXCESSIVE NOISE – All workers in vicinity of pile hammering must wear ear protection. Stay out of exclusion zones.

    Site Compound:
    • Degree C continuing site compound works.
    • Loading and unloading of deliveries.

    Site Hazards:
    • Storm Water Works – DEEP EXCAVATION – Stay out of fenced off working area
    • Pile Installation across all of site – Excessive noise & mobile plant movement. Stay out of exclusion zones and wear hearing protection where required.
    • Mobile plant movements – Be aware of all mobile plant movements. Keep out of exclusion zones.
    • Excavation – Make yourself known to excavators when moving around them.
    • Demolition – Noise & debris

현장 날씨 예보
현재 현장 날씨

마지막 업데이트 날짜: 오전 12:21
온도: 16씨 (앱 16씨)
풍속: 4KMH
최대 풍속: 4KMH @오전 12:21
오전 9시부터 비가 내림: 4.8음음
최저 기온: 15씨 @오전 12:02
최고 온도: 28씨 @오후 3:42 2026-01-14
돌풍: 6KMH
최대 돌풍: 6KMH @오전 12:21


관찰 출처 - Bureau of Meteorology
관찰 위치 - Launceston, TASMANIA
시간대 - 오스트레일리아 동부 표준시
예측 - 목요일, 15 1월

Partly cloudy.
: 11씨 맥스: 24씨
비 올 확률: 5%


예측 출처 - Bureau of Meteorology
예측 위치 - Launceston, TASMANIA
시간대 - 오스트레일리아 동부 표준시
내일 - 금요일, 16 1월

Partly cloudy.
: 11씨 맥스: 24씨
비 올 확률: 5%


중요한 현장 문서
현장에 처음 오셨나요?

이 현장의 개인 보호 장비(PPE) 요구 사항을 알고 있습니까?

현장 첫날에 올바른 안전 장비를 갖추고 있는지 확인하십시오.

현장 개인 보호 장비 요구 사항 보기

현장에 도착하면 더 빨리 작업을 시작하세요.

편리한 시간에 온라인으로 현장 등록을 완료하고 시간을 절약하세요.

등록 시작

현장에 처음 오셨나요?

이 현장의 개인 보호 장비(PPE) 요구 사항을 알고 있습니까?

현장 첫날에 올바른 안전 장비를 갖추고 있는지 확인하십시오.

현장 개인 보호 장비 요구 사항 보기

현장에 처음 오셨나요?

현장에 도착하면 더 빨리 작업을 시작하세요.

편리한 시간에 온라인으로 현장 등록을 완료하고 시간을 절약하세요.

등록 시작

;